Geomembrane Welding: Construction Procedures and Quality Control Standards

1. Pre-Construction Preparation

  • Material Inspection: Verify geomembrane specifications (type, thickness) and check for surface defects (scratches, holes, wrinkles). Ensure compatibility with welding equipment.

  • Welding Machine Check: Test machine functionality including temperature/speed controls and heating elements. Prepare backup machines and spare parts.

  • Site Preparation: Clear and level the work area; establish safety perimeters around welding zones.

2. Trial Welding

  • Parameter Setup: For HDPE geomembranes, initial settings typically range 200-250°C at 2-5m/min (adjust based on material).

  • Sample Welding: Perform test welds (≥300×300mm) using project materials.

  • Quality Verification:

    • Visually inspect seams for uniformity and defects (skips, burns).

    • Conduct peel/shear tests; recalibrate parameters if needed until optimal results are achieved.

3. Formal Welding Process

  • Alignment: Lay geomembranes smoothly with 100-150mm overlaps; eliminate wrinkles.

  • Welding Execution:

    • Maintain consistent speed/pressure during automated welding.

    • Monitor seam formation in real-time; adjust machine positioning as required.

  • Defect Repair:

    • Patch minor flaws with handheld welders or heat guns.

    • For major defects, excise and re-weld affected sections.

4. Quality Inspection

  • Visual Examination: Check for continuous, bubble-free seams without cracks or thinning.

  • Non-Destructive Testing:

    • Vacuum Test: Detect leaks using suction chambers.

    • Pressure Test: Inflate seams to verify airtightness.

  • Destructive Testing: Periodically sample seams for tensile/peel strength per ASTM standards. Investigate failures and implement corrective measures.

5. Post-Welding Protection

  • Physical Safeguards: Prohibit sharp objects, high-heat activities, or heavy traffic on welded areas.

  • Coverage: Shield geomembranes with geotextiles if follow-up work is delayed to prevent UV/weather damage.

  • Site Control: Post warning signs and assign patrols to deter unauthorized access.


Title"Geomembrane Welding Protocol: From Installation to Quality Assurance"

Key Highlights:
✔ Precision Parameters – Tailored temperature/speed for material specs
✔ Dual-Testing Approach – Combines visual, non-destructive, and destructive checks
✔ Defect Mitigation – Immediate repair protocols for seam imperfections
✔ Long-Term Preservation – Proactive measures against environmental/human damage

Applications: Landfill liners, reservoirs, mining containment, and wastewater treatment facilities.


CONTACT US

COMPANY:TAI'AN CITY RUIHENG BUILDING MATERIALS CO., LTD

Contact:Nickle Nie

Tel:008615866038408

Phone:008615866038408

Email:nickle@rhgeos.com

Add:NO.3566 LONGQUAN ROAD,TAI'AN HI-TECH ZONE,SHANDONG PROVINCE,CHINA